Indicative works for the Arlesey Relief Road

Location

The works

Date (indicative)

Traffic management

High Street South

Utility duct and drainage installation within the carriageway and footways

9 January to 3 February

Full road closure, between Goodwin Drive and Lewis Lane. This road closure will be required 24 hours. Individual households affected by this closure will be contacted directly.

Chase Hill footpath

Drainage installation within Chase Hill footpath from the High Street and for 155 metres west.

9 January to 10 March

Due to the use of heavy machinery, the footpath will be closed during these dates, with diversions in place at all times.

High Street North

Drainage and kerb realignment

6 February to 3 March

Full road closure between Goodwin Drive to the junction of Church Lane and House Lane This road closure will be required 24 hours. Individual households affected by this closure will be contacted directly.

High Street South (west)

Traffic signals infrastructure works

6 March to 29 March

(Monday to Friday only, from 9:30am to 2:30pm)

Three-way traffic lights

High Street South (east)

Traffic signals infrastructure works

30 March to 17 April

(Monday to Friday only, from 9:30am to 2:30pm)

Three-way traffic lights

High Street North (west)

Traffic signals infrastructure works

18 April to 19 May

(Monday to Friday only, from 9:30am to 2:30pm)

Three-way traffic lights

High Street North (east)

Traffic signals infrastructure works

22 May to 9 June

(Monday to Friday only, from 9:30am to 2:30pm)

Three-way traffic lights