Location |
The works |
Date (indicative) |
Traffic management |
---|---|---|---|
High Street South |
Utility duct and drainage installation within the carriageway and footways |
9 January to 3 February |
Full road closure, between Goodwin Drive and Lewis Lane. This road closure will be required 24 hours. Individual households affected by this closure will be contacted directly. |
Chase Hill footpath |
Drainage installation within Chase Hill footpath from the High Street and for 155 metres west. |
9 January to 10 March |
Due to the use of heavy machinery, the footpath will be closed during these dates, with diversions in place at all times. |
High Street North |
Drainage and kerb realignment |
6 February to 3 March |
Full road closure between Goodwin Drive to the junction of Church Lane and House Lane This road closure will be required 24 hours. Individual households affected by this closure will be contacted directly. |
High Street South (west) |
Traffic signals infrastructure works |
6 March to 29 March (Monday to Friday only, from 9:30am to 2:30pm) |
Three-way traffic lights |
High Street South (east) |
Traffic signals infrastructure works |
30 March to 17 April (Monday to Friday only, from 9:30am to 2:30pm) |
Three-way traffic lights |
High Street North (west) |
Traffic signals infrastructure works |
18 April to 19 May (Monday to Friday only, from 9:30am to 2:30pm) |
Three-way traffic lights |
High Street North (east) |
Traffic signals infrastructure works |
22 May to 9 June (Monday to Friday only, from 9:30am to 2:30pm) |
Three-way traffic lights |